← All playbooks
Project management migration

Trello → ClickUp

Move Trello boards, cards, members, comments, and files into ClickUp with the Trello importer, without treating the load as a complete copy of cover images, Butler rules, or unmapped assignees.

Typical timeline12–30 business days45–110 hours active work
Statusneeds review
Source profileTrello documentation reviewed 2026-10-27
Destination profileClickUp documentation reviewed 2026-10-27
Documentation date
Review window
Evidence3 sources
This route needs review.Use it as a planning baseline, then verify the dated sources and test with representative data before production.
Before you migrate

Should you make this move?

Both platforms have a case. Compare what you gain with what you give up before scheduling the cutover.

Current platform

Trello

Reasons to stay
  • Visual boards are immediately understandable and require almost no training
  • Structured ownership, status, and workflow views improve operational visibility
Reasons to leave
  • Dependencies, planning depth, reporting, and scale expose its simplicity
  • Custom fields, automations, history, and reporting are difficult to reproduce exactly
New platform

ClickUp

What gets better
  • A wide feature set can replace several work-management tools
  • Structured ownership, status, and workflow views improve operational visibility
What gets worse
  • Density, configuration options, and performance can overwhelm teams seeking simplicity
  • Custom fields, automations, history, and reporting are difficult to reproduce exactly
Best of the move

ClickUp: A wide feature set can replace several work-management tools. This removes a major source-side concern: Dependencies, planning depth, reporting, and scale expose its simplicity.

Worst of the move

What you lose: Visual boards are immediately understandable and require almost no training. What you inherit: Density, configuration options, and performance can overwhelm teams seeking simplicity.

Jump to a section
01At a glance

Know the shape of the move.

Transfer outcome11 features audited
Transfer outcome distributionClean transfer: 0, Partial transfer: 9, Manual rebuild: 1, Not transferred: 1.
Clean0
Partial9
Manual1
Lost1
Mapping route8 of 9 fields have a destination path

This timeline assumes

  • Up to 80 Trello boards, 25,000 cards, and 200 members
  • ClickUp Spaces exist before the Trello importer runs, or the team accepts a new Space per imported board.
  • Every imported member is mapped to a ClickUp user or an invite before anyone trusts assignees.
  • A representative board is imported and signed off before the remaining workspace.
  • The migration team records evidence for every blocking verification check.
02What transfers

What survives the move.

“Partial” and “manual” are not footnotes. They are work that must be scheduled and verified.

ItemOutcomeImpactWhat happensMitigation
Boards become ClickUp FolderspartialcriticalClickUp asks you to create Spaces first, then map each Trello board to a Folder. You can send a board into a new Space named after the Trello project, into an existing Space, or skip it. Related boards should land in the same Space.Draw the Space and Folder map before you authorize Trello. Pilot one busy board, then import related boards into that Space.
Columns as statuses or as ListspartialcriticalClickUp gives two layouts. Columns as Statuses create one List named Imported from Trello and keep To do, In progress, Review, or Done as statuses. Columns as Lists turn each column into its own List. Those Lists are for grouping, not for moving a task through a workflow.Pick one layout per board family. Do not mix both on boards that share a process. Compare card counts by original list after the load.
Assignees and unmapped memberspartialcriticalYou map Trello users to ClickUp members so assignees, history, and activity stay attached. Unmapped assignees are not preserved. ClickUp can invite by email during mapping if the person is not in the Workspace yet.Finish the email sheet before import. Invite missing people first. Keep the Trello username on any card that stays unmatched.
Attachments and cover imagespartialhighAttachments import with a 1 GB file limit. Cover images do not import. Trello does not tell you how large the attachment set is until ClickUp finishes.Download a Workspace export with raw attachments if files matter. Open a sample after import. Recreate covers that the team still uses.
Comments and recent activitypartialhighClickUp lists comments as an imported object. Trello's single-board JSON only keeps the 1,000 most recent actions, including comments. A Premium Workspace export is the path Trello documents for every comment. CSV never includes comments.Take a Workspace JSON export before import if comment history matters. Compare comment counts on decision-heavy cards.
Custom fieldspartialhighCustom fields import, then sit hidden. ClickUp tells you to open List view, click the plus control, and show Hidden imported fields before anyone can see them.Unhide imported fields on the pilot List. Archive values that did not land.
Archived cardspartialhighClickUp can import all cards or only open work. Trello CSV skips archived cards unless you add .csv to the board URL. Inbox cards cannot leave Trello until you move them onto a board.Move Inbox cards first. Decide all-cards versus open-only before the importer runs. Export archived cards from Trello if you still need them.
Checklists, tags, priority, and due datespartialhighClickUp lists checklists, tags, priority, due date, description, name, status, and date created as in-scope. You still have to confirm each one on a sample, because layout choice changes how status appears.Pilot a card that has a checklist, a due date, a priority, and tags. Rebuild anything that is blank in ClickUp.
Butler rules, Power-Ups, and board extraslostcriticalClickUp's Trello import list does not include Butler automation, Power-Ups, board backgrounds, or voting. Trello also says you cannot recreate a board from JSON or CSV.Export the Butler rule list. Recreate only the ClickUp Automations people use weekly. Keep Trello readable for Power-Up history.
Import time and Trello rate limitsmanualhighClickUp says a Trello import can take one minute to a few hours, depending on data size and Trello rate limits. It emails you when the job finishes.Import the pilot first. Do not freeze Trello on the same morning you start a large workspace load.
Live Trello writers after ClickUp intake startspartialhighThe importer is a point-in-time copy. Butler and new cards keep writing on Trello unless you stop them.Freeze Trello writes and Butler before ClickUp owns intake. Keep Trello readable through rollback.
03Field and feature mapping

Where each thing goes.

SourceDestinationMethodNotes
Trello boardClickUp Folder in a new or existing SpacetransformCreate Spaces first. Related boards share a Space.
List or columnClickUp status, or a List named after the columntransformThe layout choice locks later workflow.
Card title and descriptionTask name and descriptionautomaticKeep the Trello card URL in the description.
MembersClickUp assigneemanualUnmapped assignees are dropped.
CommentClickUp commenttransformCSV will not carry comments. Prefer a Workspace JSON archive.
AttachmentClickUp file, 1 GB limittransformCover images stay out.
Custom fieldHidden imported ClickUp field until you unhide ittransformShow Hidden imported fields on the List.
Tag, priority, or due dateMatching ClickUp fieldtransformConfirm each one on the pilot.
Cover image, Butler rule, or Power-UpNo destinationunsupportedRecreate covers and selected Automations after intake moves.
04Before you begin

Make the move recoverable.

Backup procedure

Create the source-of-truth backup

Preserve Trello boards, cards, comments, files, and members before any ClickUp write.

  1. Export each in-scope board as JSON. Take a Premium Workspace export if you need every comment.
  2. Include raw attachments in the Workspace zip when history files matter.
  3. Move Inbox cards onto a board before export. Count archived cards.
  4. Hash every export and keep a member email sheet.

Proof to capture: A signed manifest reconciles every scoped board, card class, export file, count, and hash.

Transformation · Trello-to-ClickUp mapping workbook

Space, Folder, and user map

Decide hierarchy and people before ClickUp talks to Trello.

  1. Create destination Spaces. Map each board to a Folder and a columns-as-statuses or columns-as-Lists choice.
  2. Collect a valid email for every member you will invite.
  3. Mark archived cards, Inbox cards, and boards you will skip.

Proof to capture: Save the input, output, command or tool settings, warnings, and final item counts.

Transformation · ClickUp Trello importer

Authorized Trello import

Load boards without dropping assignees or hiding custom fields.

  1. Authorize Trello, map the pilot board, and map every member.
  2. Unhide imported custom fields. Compare cards, comments, and files against the JSON export.
  3. Only then import the remaining related boards into the same Space.

Proof to capture: Save the input, output, command or tool settings, warnings, and final item counts.

05Handle with care

The things most likely to hurt.

These are operating limits. Treat every “Stop if” condition as a blocked migration, not a suggestion.

Mapping

Unmapped assignees disappear

criticalpossible likelihood

ClickUp keeps the card but drops assignees you did not map.

Consequence
Active work looks ownerless.
Mitigation
Finish the email sheet and invites first. Keep the Trello username on unmatched cards.

Stop if: A critical card has no recoverable owner.

Import

The wrong column layout hides the workflow

highpossible likelihood

Columns imported as Lists no longer move a task through To do, In progress, and Done.

Consequence
The team thinks cards vanished when they only sit in another List.
Mitigation
Pilot both layouts on a copy if you are unsure. Reconcile counts by original list.

Stop if: List counts and the signed layout disagree after the pilot.

Cutover

Both tools keep writing

criticalpossible likelihood

Butler still runs on Trello while ClickUp Automations start on the same work.

Consequence
Statuses diverge and comments duplicate.
Mitigation
Turn off Butler and freeze Trello writes before ClickUp owns intake.

Stop if: An unapproved Trello writer remains active.

06Precise timeline

Do the work in this order.

Estimate forUp to 80 Trello boards, 25,000 cards, and 200 members
Total elapsed12–30 business days
Active work45–110 hours
BufferAdd time for missing emails, a large attachment set, Inbox cards, or more than a few dozen boards.
01
Days 1–4Inventory and mode choice3–4 days
02
Days 4–7Backup and reconcile2–3 days
03
Days 7–18Map and pilot6–11 days
04
Days 16–28Final delta and switch2–6 days
05
Days 20–40Observe and close5–12 days
  1. Days 1–4 · inventory

    Inventory and mode choice

    8–16 hours active3–4 days elapsedOwner review waiting
    • Inventory boards, lists, members, Power-Ups, Butler rules, and Inbox cards.
    • Choose Space layout, column mapping, and what stays archived in Trello.

    Depends on: Trello Workspace admin and ClickUp Workspace admin access

    Stop / go checkpoint

    Export?

    Go when: Every critical board has an owner and disposition.

    Stop when: Column layout, emails, or consent is unclear.

  2. Days 4–7 · backup

    Backup and reconcile

    6–12 hours active2–3 days elapsedWorkspace export processing waiting
    • Create JSON and attachment exports.
    • Reconcile counts, hashes, and the member email sheet.

    Depends on: Approved inventory

    Stop / go checkpoint

    Transform?

    Go when: Source totals and export manifests agree.

    Stop when: Any critical board, comment class, or attachment set is absent.

  3. Days 7–18 · pilot

    Map and pilot

    14–45 hours active6–11 days elapsedOwner review of the sample waiting
    • Import one board that includes a checklist, a file, a custom field, and a member without ClickUp access.
    • Unhide imported fields and compare cards, comments, and attachments.

    Depends on: Verified backup

    Stop / go checkpoint

    Scale?

    Go when: Pilot mappings, access, and evidence pass.

    Stop when: Any critical check fails or a count is unexplained.

  4. Days 16–28 · cutover

    Final delta and switch

    6–24 hours active2–6 days elapsedRemaining board imports waiting
    • Freeze Trello writes and Butler.
    • Import the remaining boards, switch intake, and run blocking checks.

    Depends on: Passed pilot and approved rollback

    Stop / go checkpoint

    Open production?

    Go when: Every in-scope card is accounted for and ClickUp owns intake.

    Stop when: A Trello writer remains active or a blocking check fails.

  5. Days 20–40 · observe

    Observe and close

    4–18 hours active5–12 days elapsedOne planning cycle waiting
    • Watch one complete planning and delivery cycle.
    • Sign the verification report before you close rollback.

    Depends on: Verified cutover

    Stop / go checkpoint

    Close rollback?

    Go when: No trigger occurs during the agreed observation period.

    Stop when: Work, access, or reporting regresses.

07The point of change

Cut over with a way back.

Go live

Cutover

Make ClickUp the only intake system without losing the final Trello delta.

Recommended window: After the last weekly review, on a staffed low-change morning.

  1. Freeze Trello writes, Butler, and new card intake.
  2. Export and import the final changed boards or cards.
  3. Switch forms, email, and client links to ClickUp.
  4. Run every blocking check and keep Trello readable.
  5. Keep the source intact through the rollback window.

Proof to capture: ClickUp owns intake, every in-scope Trello card is accounted for, and every blocking check has evidence.

Return to safety

Rollback

Return intake to Trello without losing ClickUp-era changes.

Deadline: Within one planning cycle and before Trello Workspace exports, credentials, or boards are changed.

  1. Stop new writes and Automations in ClickUp.
  2. Restore Trello access, Butler, and intake.
  3. Export the ClickUp post-cutover delta.
  4. Review and apply safe destination-era changes to Trello.
  5. Run the same blocking checks against Trello.

Proof to capture: Trello again owns intake with current work and no duplicate ClickUp action.

Rollback immediately when
  • Unexplained missing Trello cards
  • Missing or exposed comments or files
  • Duplicate production action
  • Failed access or assignment check
  • A critical workflow has no safe ClickUp replacement
08Verification report

Prove the migration worked.

Every blocking check must pass. Capture the evidence before cleanup begins.

0%
Interactive report preview0 / 8 checks passed
PassIDCheckMethodExpected resultEvidence
V-01BlockingCard reconciliationCompare every in-scope Trello card to a ClickUp task, archive, or exclusion.100% of scoped cards are accounted for.Card ledger.
V-02BlockingColumns and layoutCompare each Trello list to a ClickUp status or List.Placement matches the signed columns-as-statuses or columns-as-Lists map.Hierarchy report.
V-03BlockingAssignees and invitesTest mapped, invited, and unmatched members.Assignments follow the sheet. Unmatched usernames remain on the task.User matrix.
V-04BlockingCustom fields visibleOpen the pilot List and show Hidden imported fields.Each imported custom field is visible, archived, or excluded.Field exception list.
V-05BlockingComments and filesOpen decision-heavy cards and their attachments as ordinary users.Required history and files work without a Trello login. Covers that matter were recreated.Context log.
V-06BlockingArchived and Inbox cardsCompare archived Trello items and former Inbox cards to the import option you chose.Each item is imported, skipped with a signed reason, or still on a Trello board.Archive ledger.
V-07BlockingSingle writerCreate and update a test card after freeze.Only ClickUp acts. Trello stays still.Automation log.
V-08BlockingPermissionsTest admin, member, guest, and unauthorized accounts.Least privilege holds.Access matrix.
09Post-migration cleanup

Remove the scaffolding safely.

Safe after: One complete planning cycle, at least seven stable days, and owner sign-off on every blocking check.

  1. Archive Trello exports, maps, and verification evidence.
  2. Revoke the Trello authorization used for the ClickUp importer.
  3. Remove obsolete Butler rules, Power-Ups, and webhooks.
  4. Keep Trello read-only through the approved retention window.
  5. Cancel paid Trello plans only after billing, legal, and recovery review.
  6. Schedule the next ClickUp backup, access, and playbook review.
10Experiences from the field

When the plan met reality.

First-hand accounts are preferred. Vendor case studies are labeled, and every note below is an editorial paraphrase—follow the link for the full context.

First-person accountCarrylove Designs

Small Business CRMs: How ClickUp Keeps My Business Organized2021

The Carrylove Designs owner wrote on 15 March 2021 that Trello worked for a two-person shop and failed as the studio grew toward nine people. Missed notifications when clients forgot to tag a designer, weak task sharing, and no time tracking were the reasons to leave. They hired a ClickUp workflow specialist because their Signature Experience already had a four-part client process, and they rebuilt the map around onboarding through launch instead of week columns. They kept Trello for internal copy, captions, templates, and blueprints. The stated mistake was switching during a pandemic busy season. The post is a process diary. It does not describe ClickUp's Trello importer, cover images, or custom-field hiding.

What they recommend
  • Rebuild the client process in ClickUp before you import boards, the way Carrylove mapped the Signature Experience instead of copying week columns.
  • Treat this post as a staffing and timing note. Still pilot ClickUp's Trello importer if you need historical comments and files.
Worth noticing
  • They left Trello because notifications and time tracking failed at a larger headcount, not because an importer failed.
  • They kept Trello as a side archive, so a full board cutover was not the story they told.
First-person accountJessica Rodriguez · Jessica Rodriguez

Trello vs ClickUp: Why we moved from Trello to ClickUp2022

Jessica Rodriguez wrote on 21 March 2022 that Trello was easy when the business was her plus a VA: visual boards, templates, and a free plan with ten boards. Growth made one-board-at-a-time visibility the bottleneck. Tasks slipped because she could not see every project at once, and workarounds ate more time than the work. ClickUp won on list, board, calendar, Gantt, and table views, per-person dashboards, custom statuses, and guest access for short-term contractors. She warns that ClickUp takes setup time and that templates can limit a shop that needs its own structure. The post compares daily use. It does not describe a Trello board import, assignee mapping, or attachment limits.

What they recommend
  • If the reason to leave is cross-board visibility, test ClickUp dashboards and custom statuses with the live team before you import history.
  • Budget setup time. Rodriguez says figuring out Spaces and handing the build to a teammate mattered more than using a template.
Worth noticing
  • The switch was about seeing all projects at once, not about a documented data-loss event.
  • Guest access for contractors was a billed-seat reason, so a card import alone would not have finished the move.
Sources and evidence

Verify against the primary material.

Platform behavior changes. Check these sources and the review dates above before executing a production migration.

  1. ClickUp: import from TrelloAccessed 2026-10-27
  2. Trello: export data from TrelloAccessed 2026-10-27
  3. ClickUp: import to ClickUpAccessed 2026-10-27